Project Detail Report
| Status | Proposed |
|---|---|
| Type | Sewerage |
| Agency | Lake Victoria North Water Works Development Agency |
| Program | Kenya Towns Sustainable Water Supply and Sanitation Programme |
| Progress | 0.00% |
| County | Busia |
|---|---|
| Constituency | Teso South, Matayos |
| Ward | Alupe, Angolot, Amerikwai, Mjini, Mayenje, Korinda |
| Setting | Urban |
| Coordinates | 0.460138, 34.113347 |
| Start Date | N/A |
|---|---|
| Planned End Date | N/A |
| Actual End Date | N/A |
| Contractor | N/A |
| Consultant | N/A |
| Target Areas | N/A |
| Scope of Works | Rehabilitation and extension of existing sewer lines to an additional of 45.1km including trunk, Expansion of waste water treatment of additional capacity of 16,939m3/day, Construction of on-site sanitation facilities (ablution blocks with biodigester) |
| Impacts | The project will help reduce waterborne diseases due to improved sanitation which will lead to better overall health and reduced healthcare costs. Improved sanitation will increase productivity in the workforce, leading to improved livelihoods and economic growth. |
| Challenges | N/A |
| Remarks | N/A |
| Total Contract Sum (GoK + Foreign) | KES 0.00 |
|---|---|
| GoK Contract Sum | KES 0.00 |
| Foreign Contract Sum | KES 0.00 |
| Cumulative Expenditure | KES 0.00 |
| Outstanding Cost | KES 0.00 |