Keben Dam Water Supply Project

Project Detail Report

Overview

StatusOngoing
TypeLarge Dam
AgencyLake Victoria North Water Works Development Agency
ProgramGovernment of Kenya Funded Development programme
Progress90.00%

Location Information

CountyNandi
ConstituencyChemundu, Kapsabet, Kilibwoni, Nandi Hills, Ol’lessos, Kaptumo
WardKapsabet, Nandi Hills, Lessos,Baraton, Chepterit,Kibabet, Chepkunyuk,Tartar, Siwo,Sochoi, Koilot
SettingUrban
Coordinates0.205606, 35.297178

Timeline & Impact

Start DateN/A
Planned End DateN/A
Actual End DateN/A
ContractorN/A
ConsultantN/A
Target AreasN/A
Scope of WorksPreliminaries & General Items. CFU & Masonry Tank. Distribution Lines. Elevated Steel Tank. Construction of Masonry Tank. Construction of Staff Houses. Pump Installation and Fencing. Construction of Dam
ImpactsThe project will lead to reduction in waterborne diseases due to access to clean water and improved sanitation, leading to better overall health and reduced healthcare costs. Increased school attendance especially for girls as they spend less time collecting water and managing sanitation needs. Access to clean water and sanitation will increase productivity in the workforce, leading to improved livelihoods and economic growth, women and girls often bear the burden of collecting water, so improved water access will empower them and provide more time for other activities
ChallengesN/A
RemarksN/A

Project Cost

Total Contract Sum (GoK + Foreign)KES 0.00
GoK Contract SumKES 0.00
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 0.00
Outstanding CostKES 0.00