Project Detail Report
| Status | Proposed |
|---|---|
| Type | Water Supply |
| Agency | Lake Victoria North Water Works Development Agency |
| Program | Government of Kenya Funded Development programme |
| Progress | 0.00% |
| County | Busia |
|---|---|
| Constituency | Teso North Teso South |
| Ward | Malaba ,Mianga |
| Setting | Rural |
| Coordinates | , |
| Start Date | N/A |
|---|---|
| Planned End Date | N/A |
| Actual End Date | N/A |
| Contractor | N/A |
| Consultant | N/A |
| Target Areas | N/A |
| Scope of Works | Construction of 1nr 200m3 and 1nr 48m3 elevated steel tank at Malaba and Mianga, Laying of 30 km HDPE pipelines of varying dimeters ranging from DN 75 TO 32mm, Construction of 3 No Water Kiosks, 200 consumer connections. |
| Impacts | There will be reduction in waterborne diseases due to access to clean water leading to better overall health and reduced healthcare costs. There will be increased school attendance especially for girls as they spend less time collecting water. Access to clean water will increase productivity in the workforce, leading to improved livelihoods and economic growth, women and girls often bear the burden of collecting water, so improved water access will empower them and provide more time for other activities |
| Challenges | N/A |
| Remarks | N/A |
| Total Contract Sum (GoK + Foreign) | KES 0.00 |
|---|---|
| GoK Contract Sum | KES 0.00 |
| Foreign Contract Sum | KES 0.00 |
| Cumulative Expenditure | KES 0.00 |
| Outstanding Cost | KES 0.00 |
| Source | Type | Amount (KES) |
|---|---|---|
| Gok | Grant | 40,000,000.00 |