| Start Date | N/A |
| Planned End Date | N/A |
| Actual End Date | N/A |
| Contractor | N/A |
| Consultant | N/A |
| Target Areas | Kabuyefwe |
| Scope of Works | Spring protection
Installation of solar-powered water pump system
Rehabilitation of pump house and 50m3 masonry sump
5,600m long, 90mm in diameter HDPE Rising main from the spring intake to the
50m3 masonry tank atMfupii Market
9km long HDPE Distribution lines as last mile connectivity component
Construction of 4 number Water kiosks
Consh·uction of 7 No Communal water points at public institutions within the area
Fabrication and construction of 50m3 elevated tank at Mfupi junction
Fencing of about 300m long ia n perimeter around the water source and the reservoir
area etc. |
| Impacts | Reduction in waterborne diseases due to access to clean water and improved sanitation, leading to better overall health and reduced healthcare costs. Increased school attendance especially for girls as they spend less time collecting water and managing sanitation needs. Access to clean water and sanitation will increase productivity in the workforce, leading to improved livelihoods and economic growth, women and girls often bear the burden of collecting water, so improved water access will empower them and provide more time for other activities |
| Challenges | Late disbursement of funds |
| Remarks | Awaiting disbursment of funds to advertise for construction works |