Central Naitiri Community water project

Project Detail Report

Overview

StatusProposed
TypeWater Supply
AgencyLake Victoria North Water Works Development Agency
ProgramNational Harvesting and Ground Water Exploration
Progress0.00%

Location Information

CountyBungoma
ConstituencyTongaren
WardNaitiri/kabuyefwe ward
SettingRural
Coordinates,

Timeline & Impact

Start DateN/A
Planned End DateN/A
Actual End DateN/A
ContractorN/A
ConsultantN/A
Target AreasKabuyefwe
Scope of WorksSpring protection Installation of solar-powered water pump system Rehabilitation of pump house and 50m3 masonry sump 5,600m long, 90mm in diameter HDPE Rising main from the spring intake to the 50m3 masonry tank atMfupii Market 9km long HDPE Distribution lines as last mile connectivity component Construction of 4 number Water kiosks Consh·uction of 7 No Communal water points at public institutions within the area Fabrication and construction of 50m3 elevated tank at Mfupi junction Fencing of about 300m long ia n perimeter around the water source and the reservoir area etc.
ImpactsReduction in waterborne diseases due to access to clean water and improved sanitation, leading to better overall health and reduced healthcare costs. Increased school attendance especially for girls as they spend less time collecting water and managing sanitation needs. Access to clean water and sanitation will increase productivity in the workforce, leading to improved livelihoods and economic growth, women and girls often bear the burden of collecting water, so improved water access will empower them and provide more time for other activities
ChallengesLate disbursement of funds
RemarksAwaiting disbursment of funds to advertise for construction works

Project Cost

Total Contract Sum (GoK + Foreign)KES 0.00
GoK Contract SumKES 0.00
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 0.00
Outstanding CostKES 0.00

Funding Sources

SourceTypeAmount (KES)
Gok Grant 10,000,000.00

Beneficiaries

Target Households875
Target Population3,500