Ndalu-Sinoko water Project

Project Detail Report

Overview

StatusProposed
TypeBorehole
AgencyLake Victoria North Water Works Development Agency
ProgramLake Victoria North WWDA Projects.
Progress0.00%

Location Information

CountyBungoma
ConstituencyTongaren
WardNdalu
SettingRural
Coordinates0.842772, 34.992570

Timeline & Impact

Start DateN/A
Planned End DateN/A
Actual End DateN/A
ContractorN/A
ConsultantN/A
Target AreasN/A
Scope of WorksDrilling, Construction of Storage tank, Electromechanical and Civil Works
ImpactsReduction in waterborne diseases due to access to clean water and improved sanitation, leading to better overall health and reduced healthcare costs. Increased school attendance especially for girls as they spend less time collecting water and managing sanitation needs. Access to clean water and sanitation will increase productivity in the workforce, leading to improved livelihoods and economic growth, women and girls often bear the burden of collecting water, so improved water access will empower them and provide more time for other activities
ChallengesN/A
RemarksAwaiting disbursment of funds to advertise for construction works

Project Cost

Total Contract Sum (GoK + Foreign)KES 0.00
GoK Contract SumKES 0.00
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 0.00
Outstanding CostKES 0.00

Funding Sources

SourceTypeAmount (KES)
Gok Grant 10,000,000.00

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2023/24 Approved GOK 5,000,000.00