St. Kizito Sirende Borehole Project

Project Detail Report

Overview

StatusOngoing
TypeBorehole
AgencyLake Victoria North Water Works Development Agency
ProgramLake Victoria North WWDA Projects.
Progress10.00%

Location Information

CountyBungoma
ConstituencyTongaren
WardNaitiri
SettingRural
Coordinates0.716591, 34.711520

Timeline & Impact

Start DateN/A
Planned End DateN/A
Actual End DateN/A
ContractorHydrotech Associates Limited
ConsultantN/A
Target AreasKizito
Scope of WorksDrilling, Construction of Storage tank, Electromechanical and Civil Works
ImpactsReduction in waterborne diseases due to access to clean water and improved sanitation, leading to better overall health and reduced healthcare costs. Increased school attendance especially for girls as they spend less time collecting water and managing sanitation needs. Access to clean water and sanitation will increase productivity in the workforce, leading to improved livelihoods and economic growth, women and girls often bear the burden of collecting water, so improved water access will empower them and provide more time for other activities
ChallengesN/A
RemarksN/A

Project Cost

Total Contract Sum (GoK + Foreign)KES 2,492,345.00
GoK Contract SumKES 2,492,345.00
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 0.00
Outstanding CostKES 0.00

Funding Sources

SourceTypeAmount (KES)
Gok Grant 5,000,000.00

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2024/25 Allocated GOK 5,000,000.00

Beneficiaries

Target Households450
Target Population1,800