Borehole drilling and capping for the Kipkoror School Water Project

Project Detail Report

Overview

StatusProposed
TypeBorehole
AgencyLake Victoria North Water Works Development Agency
ProgramWater for Schools
Progress0.00%

Location Information

CountyNandi
ConstituencyNandi Hills
WardChepkunyuk
SettingN/A
Coordinates,

Timeline & Impact

Start DateN/A
Planned End DateN/A
Actual End DateN/A
ContractorWinteam International Limited
ConsultantN/A
Target AreasKipkoror
Scope of WorksDrilling, Construction of Storage tank, Electromechanical and Civil Works
ImpactsReduction in waterborne diseases due to access to clean water and improved sanitation, leading to better overall health and reduced healthcare costs. Increased school attendance especially for girls as they spend less time collecting water and managing sanitation needs. Access to clean water and sanitation will increase productivity in the workforce, leading to improved livelihoods and economic growth, women and girls often bear the burden of collecting water, so improved water access will empower them and provide more time for other activities
ChallengesN/A
RemarksN/A

Project Cost

Total Contract Sum (GoK + Foreign)KES 3,001,213.00
GoK Contract SumKES 3,001,213.00
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 2,921,213.33
Outstanding CostKES 0.00

Beneficiaries

Target Households1,000
Target Population5,000