Project Detail Report
| Status | Proposed |
|---|---|
| Type | Water Supply |
| Agency | Lake Victoria North Water Works Development Agency |
| Program | Lake Victoria North WWDA Projects. |
| Progress | 0.00% |
| County | N/A |
|---|---|
| Constituency | N/A |
| Ward | N/A |
| Setting | Rural |
| Coordinates | , |
| Start Date | N/A |
|---|---|
| Planned End Date | N/A |
| Actual End Date | N/A |
| Contractor | N/A |
| Consultant | N/A |
| Target Areas | N/A |
| Scope of Works | Construction of kimama tank(bill2), Construction of Cheptais 225m3 capacity tank(bill 3), Construction of Sirisia 225m3 capacity tank (bill4), New pipeline (namwela and sirisia–butonge), Water kiosks, Rehabilitation works at t/works, Rehabilitation of old tanks, Rehabilitation of old pipeline, Installation of air valves and washouts |
| Impacts | Reduction in waterborne diseases due to access to clean water and improved sanitation, leading to better overall health and reduced healthcare costs. Increased school attendance especially for girls as they spend less time collecting water and managing sanitation needs. Access to clean water and sanitation will increase productivity in the workforce, leading to improved livelihoods and economic growth, women and girls often bear the burden of collecting water, so improved water access will empower them and provide more time for other activities |
| Challenges | N/A |
| Remarks | N/A |
| Total Contract Sum (GoK + Foreign) | KES 45,228,214.50 |
|---|---|
| GoK Contract Sum | KES 45,228,214.50 |
| Foreign Contract Sum | KES 0.00 |
| Cumulative Expenditure | KES 0.00 |
| Outstanding Cost | KES 0.00 |