Project Detail Report
| Status | Completed |
|---|---|
| Type | Borehole |
| Agency | Tanathi Water Works Development Agency |
| Program | Drilling and Equipping of Boreholes |
| Progress | 100.00% |
| County | Kitui |
|---|---|
| Constituency | Kitui South |
| Ward | Kyatune/Mutomo |
| Setting | Rural |
| Coordinates | -1.797030, 38.174630 |
| Start Date | 2021-02-07 |
|---|---|
| Planned End Date | 2023-01-09 |
| Actual End Date | 2023-01-09 |
| Contractor | Facetime Company Limited |
| Consultant | N/A |
| Target Areas | Community Schools |
| Scope of Works | • Drilling, Casing and Test Pumping • Installation of submersible pump, • Solar installation with steel mounting structure, • Distribution pipeline • Water kiosks, |
| Impacts | The project serves the target area with clean, safe, and affordable water |
| Challenges | The project was delayed due to delayed exchequer release |
| Remarks | The project is complete, operational, and has been handed over to the community |
| Total Contract Sum (GoK + Foreign) | KES 9,800,704.00 |
|---|---|
| GoK Contract Sum | KES 9,800,704.00 |
| Foreign Contract Sum | KES 0.00 |
| Cumulative Expenditure | KES 9,800,704.00 |
| Outstanding Cost | KES 0.00 |
| Source | Type | Amount (KES) |
|---|---|---|
| Gok | Grant | 10,000,000.00 |
| Fiscal Year | Stage | Funding Side | Amount (KES) |
|---|---|---|---|
| 2022/23 | Approved | GOK | 9,800,704.00 |
| Target Households | 240 |
|---|---|
| Target Population | 1,200 |