Project Detail Report
| Status | Ongoing |
|---|---|
| Type | River Intake |
| Agency | Tanathi Water Works Development Agency |
| Program | Kenya Towns Sustainable Water Supply and Sanitation Program (KTSWSSP) |
| Progress | 55.00% |
| County | Machakos |
|---|---|
| Constituency | Mwala |
| Ward | Muthetheni |
| Setting | Urban |
| Coordinates | -1.243920, 37.444600 |
| Start Date | 2024-01-01 |
|---|---|
| Planned End Date | 2025-01-12 |
| Actual End Date | 2025-01-12 |
| Contractor | Zhongmei Engineering Group Limited JV Visrom Company Ltd |
| Consultant | CAS Consultants |
| Target Areas | Kalimoni |
| Scope of Works | • Intake weir & Intake works at Munyu River • Treatment works of 6,600 m3/day |
| Impacts | The project upon completion will serve the target area with clean, safe, and affordable water |
| Challenges | Slow IPC Payment processes |
| Remarks | The project ongoing and is within schedule |
| Total Contract Sum (GoK + Foreign) | KES 589,231,156.80 |
|---|---|
| GoK Contract Sum | KES 589,231,156.80 |
| Foreign Contract Sum | KES 0.00 |
| Cumulative Expenditure | KES 589,231,156.80 |
| Outstanding Cost | KES 0.00 |
| Source | Type | Amount (KES) |
|---|---|---|
| Gok | Grant | 235,692,463.00 |
| Adb | Loan | 589,231,156.80 |
| Fiscal Year | Stage | Funding Side | Amount (KES) |
|---|---|---|---|
| 2021/22 | Approved | FOREIGN | 368,269,473.00 |
| 2021/22 | Approved | GOK | 58,923,116.00 |
| 2022/23 | Approved | FOREIGN | 383,000,252.00 |
| 2022/23 | Approved | GOK | 61,280,040.00 |
| 2023/24 | Approved | FOREIGN | 515,577,262.00 |
| 2023/24 | Approved | GOK | 82,492,362.00 |
| 2024/25 | Allocated | FOREIGN | 147,307,789.00 |
| 2024/25 | Allocated | GOK | 23,569,246.00 |
| Target Households | 5,000 |
|---|---|
| Target Population | 25,000 |