Overview
| Status | Completed |
| Type | Water Supply |
| Agency | Central Rift Valley Water Works Development Agency |
| Program | Cross- County Bulk Water & Sanitation Program |
| Progress | 100.00% |
Location Information
| County | Laikipia |
| Constituency | Laikipia West |
| Ward | Mukurweini |
| Setting | Rural |
| Coordinates | 0.315980, 36.808628 |
Timeline & Impact
| Start Date | N/A |
| Planned End Date | N/A |
| Actual End Date | N/A |
| Contractor | N/A |
| Consultant | N/A |
| Target Areas | Mukurweini Ward and its environs |
| Scope of Works | Construction of Intake weir, pumping station, Sump, Pipeline and 2No. 225 CM Masonry tanks |
| Impacts | Increased water coverage in Mukurweini Ward and its Environs |
| Challenges | No challenges |
| Remarks | Works complete |
Project Cost
| Total Contract Sum (GoK + Foreign) | KES 23,737,734.90 |
| GoK Contract Sum | KES 23,737,734.90 |
| Foreign Contract Sum | KES 0.00 |
| Cumulative Expenditure | KES 0.00 |
| Outstanding Cost | KES 0.00 |
Funding Sources
| Source | Type | Amount (KES) |
| Gok |
Grant |
23,737,734.90 |
Budget Allocations by Fiscal Year
| Fiscal Year | Stage | Funding Side | Amount (KES) |
| 2021/22 |
Approved |
GOK |
18,143,277.66 |
Beneficiaries
| Target Households | 600 |
| Target Population | 3,000 |