Overview
| Status | Ongoing |
| Type | Water Supply River intake |
| Agency | Central Rift Valley Water Works Development Agency |
| Program | GOK Funded Projects |
| Progress | 30.00% |
Location Information
| County | Nyandarua |
| Constituency | Kipipiri |
| Ward | Kipipiri |
| Setting | Urban |
| Coordinates | -0.392997, 36.480363 |
Timeline & Impact
| Start Date | N/A |
| Planned End Date | 2022-01-08 |
| Actual End Date | 2022-01-08 |
| Contractor | N/A |
| Consultant | N/A |
| Target Areas | Kipipiti region |
| Scope of Works | Construction of Intake weir. Gravity main and Rehabilitation of Existing network |
| Impacts | Improved access to water supply |
| Challenges | Slow contractor mobilization |
| Remarks | aiting contractor to re mobilize |
Project Cost
| Total Contract Sum (GoK + Foreign) | KES 17,177,624.10 |
| GoK Contract Sum | KES 17,177,624.10 |
| Foreign Contract Sum | KES 0.00 |
| Cumulative Expenditure | KES 0.00 |
| Outstanding Cost | KES 0.00 |
Funding Sources
| Source | Type | Amount (KES) |
| Gok |
Grant |
17,177,624.10 |
Budget Allocations by Fiscal Year
| Fiscal Year | Stage | Funding Side | Amount (KES) |
| 2021/22 |
Approved |
GOK |
17,177,624.10 |
| 2022/23 |
Approved |
GOK |
17,177,624.10 |
Beneficiaries
| Target Households | 400 |
| Target Population | 2,000 |