Molo, Njoro, Elburgon, Salgaa and Mau Summit Water Supply and Sewerage Project cluster

Project Detail Report

Overview

StatusProposed
TypeSewerage and Sanitation Project
AgencyCentral Rift Valley Water Works Development Agency
ProgramNational Urban Water Supply and Sanitataion Program (NUWSSP) Ph II
Progress0.00%

Location Information

CountyNakuru
ConstituencyNjoro
WardNjoro
SettingUrban
Coordinates-0.375518, 35.942823

Timeline & Impact

Start DateN/A
Planned End DateN/A
Actual End DateN/A
ContractorN/A
ConsultantN/A
Target AreasN/A
Scope of WorksRehabilitation of existing water supply and augmentation system, Construction of sewerage system
ImpactsN/A
ChallengesN/A
RemarksThe Government is seeking to implement the project under National Urban Water Supply and Sanitation Program Phase II

Project Cost

Total Contract Sum (GoK + Foreign)KES 0.00
GoK Contract SumKES 0.00
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 0.00
Outstanding CostKES 0.00