Othaya Sewerage Project (Last Mile Connectivity Phase I)

Project Detail Report

Overview

StatusCompleted
TypeSanitation
AgencyTana Water Works Development Agency
ProgramKenya Towns Sustainable Water Supply and Sanitation Program (KTSWSSP)
Progress100.00%

Location Information

CountyNyeri
ConstituencyOthaya
WardMahiga
SettingUrban
Coordinates-0.548880, 36.945000

Timeline & Impact

Start Date2019-02-01
Planned End Date2020-03-01
Actual End DateN/A
Contractorvisrom limited
ConsultantN/A
Target AreasOthaya Town Environs
Scope of Works Laying of 7.8 Km Sewer Lines of Diameter 100mm- 225mm  Rehabilitation of an ablution block  Construction of 1No. sludge drying bed Addendum Works  Kanyange sewerline, Kagonye ablution block, micro-tunneling works
ImpactsConnects Othaya town with reliable sewer system.
ChallengesDelays caused by the tax exemption approval process and delay in payment of Advance Payment
RemarksImprovement of sanitation services within Othaya town The project is complete and operational

Project Cost

Total Contract Sum (GoK + Foreign)KES 78,638,020.15
GoK Contract SumKES 0.00
Foreign Contract SumKES 78,638,020.15
Cumulative ExpenditureKES 78,622,670.93
Outstanding CostKES 0.00

Funding Sources

SourceTypeAmount (KES)
Adb Loan 78,638,020.15

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2021/22 Approved FOREIGN 18,734,053.50
2021/22 Approved GOK 2,829,000.00
2022/23 Approved FOREIGN 18,010,659.00
2022/23 Approved GOK 1,677,000.00
2023/24 Approved FOREIGN 16,117,000.00
2023/24 Approved GOK 200,000.00
2024/25 Allocated FOREIGN 8,000,000.00
2024/25 Allocated GOK 1,000,000.00

Beneficiaries

Target Households600
Target Population3,000