Overview
| Status | Completed |
| Type | Water Supply |
| Agency | Tana Water Works Development Agency |
| Program | Water Harvesting Program |
| Progress | 100.00% |
Location Information
| County | Nyeri |
| Constituency | Mathira |
| Ward | Iriani |
| Setting | Rural |
| Coordinates | 0.633361, 36.633361 |
Timeline & Impact
| Start Date | 2023-06-06 |
| Planned End Date | 2024-07-06 |
| Actual End Date | N/A |
| Contractor | Sori Investment Ltd |
| Consultant | N/A |
| Target Areas | Karatina Town and its Environs |
| Scope of Works | Construction of new intake and inlet chamber
Laying of raw water gravity mainline
Construction of 10m3 Break Pressure Tank (BPT) |
| Impacts | The project has facilitated farming activity within the area. |
| Challenges | Late GOK disbursement and contactor citing financial constrains. |
| Remarks | Improving access to safe water for domestic use. |
Project Cost
| Total Contract Sum (GoK + Foreign) | KES 42,949,940.00 |
| GoK Contract Sum | KES 42,949,940.00 |
| Foreign Contract Sum | KES 0.00 |
| Cumulative Expenditure | KES 34,724,200.00 |
| Outstanding Cost | KES 8,225,740.00 |
Funding Sources
| Source | Type | Amount (KES) |
| Gok |
Grant |
42,949,940.00 |
Beneficiaries
| Target Households | 800 |
| Target Population | 4,000 |