Rehabilitation and Augmentation of Endarasha Water Supply Project

Project Detail Report

Overview

StatusOngoing
TypeWater Supply
AgencyTana Water Works Development Agency
ProgramCross- County Bulk Water & Sanitation Program
Progress80.00%

Location Information

CountyNyeri
ConstituencyKieni
WardMwiyogo/Endara Sha
SettingRural
Coordinates,

Timeline & Impact

Start Date2023-03-06
Planned End DateN/A
Actual End DateN/A
ContractorPower and Solar Group Limited
ConsultantN/A
Target AreasEndarasha and its environs
Scope of Works- Laying of a 7.1km Kamianda-Endarasha mainline. - Laying of 1.48km Endarasha-Kanyiriri mainline. - Laying of 4.4km Kamigogo intake to Charity - Construction of 2 No 5m3 Break Pressure Tanks (BPT). - Rehabilitation of 2 No existing tanks to serve as Break Pressure Tanks.
ImpactsProvision od emplyment. More than 1300 Households will stand to benefit from the project
ChallengesSlow progress by the contractor citing financial constraints
RemarksImprovement acees to clean water

Project Cost

Total Contract Sum (GoK + Foreign)KES 14,823,900.00
GoK Contract SumKES 14,823,900.00
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 5,718,260.00
Outstanding CostKES 0.00

Funding Sources

SourceTypeAmount (KES)
Gok Grant 14,823,900.00

Beneficiaries

Target Households2,755
Target Population12,775