Mathira Community Water Project – Phase II

Project Detail Report

Overview

StatusOngoing
TypeWater Supply
AgencyTana Water Works Development Agency
ProgramCross- County Bulk Water & Sanitation Program
Progress1.00%

Location Information

CountyNyeri
ConstituencyMathira
WardKonyu
SettingRural
Coordinates0.633361, 36.633361

Timeline & Impact

Start DateN/A
Planned End Date2025-06-06
Actual End DateN/A
ContractorInternal
ConsultantN/A
Target AreasMathira
Scope of Works·  Construction of 1 No. masonry tank and laying of laying 17km water pipeline for Ragati Karura Water Project ·  Laying of 4km water pipeline for Kanjuri Water Project ·  Construction of 1 No. masonry tank and laying of laying 0.7km water pipeline for Kanjuri High School Water Project ·  Construction of 1 No. masonry tank and laying of laying 13km water pipeline for Ndumano Water Project ·  Installation of pipeline fittings and household water connections for Magutu Water Project
ImpactsImprove access to clean water and provision of direct employment to locals
ChallengesDelay in the GOK counter fund.
RemarksImprovement access to clean water

Project Cost

Total Contract Sum (GoK + Foreign)KES 162,000,000.00
GoK Contract SumKES 162,000,000.00
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 22,972,353.00
Outstanding CostKES 0.00

Funding Sources

SourceTypeAmount (KES)
Gok Grant 162,000,000.00

Beneficiaries

Target Households2,000
Target Population10,000