Contsruction of Tetu Aguthi Water Supply project

Project Detail Report

Overview

StatusOngoing
TypeWater Supply
AgencyTana Water Works Development Agency
ProgramCross- County Bulk Water & Sanitation Program
Progress1.00%

Location Information

CountyNyeri
ConstituencyTetu
WardAguthi
SettingUrban
Coordinates0.491700, 37.002500

Timeline & Impact

Start DateN/A
Planned End DateN/A
Actual End DateN/A
ContractorMamudowa Ltd
ConsultantN/A
Target AreasTetu
Scope of WorksConstruction of 1 no. Cross weir and an intake chamber. Laying of DN 355 mm – 17 km long RWGM inside the forest. Construction of Treatment works capacity 10,0000 m3 per day at the edge of the forest. Construction of 1 No. -500m3 Clear Water Tank tank at the T/works. Removal, Replacement and Disposal of 250mm Asbestos Pipeline (a distance of upto 15km).
ImpactsImprove access to clean water and provision of direct employment to locals
ChallengesDelay in the GOK counter fund and beuracracy within KFS making it hard to acquire their licences.
RemarksImprovement access to clean water

Project Cost

Total Contract Sum (GoK + Foreign)KES 680,692,072.30
GoK Contract SumKES 680,692,072.30
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 0.00
Outstanding CostKES 0.00

Funding Sources

SourceTypeAmount (KES)
Gok Grant 680,692,072.30

Beneficiaries

Target Households2,000
Target Population10,000