Overview
| Status | Proposed |
| Type | Water Supply Project |
| Agency | Tana Water Works Development Agency |
| Program | National Urban Water Supply and Sanitataion Program (NUWSSP) Ph II |
| Progress | 0.00% |
Location Information
| County | Nyeri |
| Constituency | Kieni |
| Ward | Naromoru/Kiamathaga |
| Setting | Urban |
| Coordinates | -0.167560, 37.021290 |
Timeline & Impact
| Start Date | N/A |
| Planned End Date | N/A |
| Actual End Date | N/A |
| Contractor | N/A |
| Consultant | N/A |
| Target Areas | Naromoru and environs |
| Scope of Works | Construction of 10,000m3/d conventional water treatment plant |
| Impacts | Improve access to clean water and provision of direct employment to locals |
| Challenges | Awaiting Funds allocation |
| Remarks | Designs complete |
Project Cost
| Total Contract Sum (GoK + Foreign) | KES 1,300,000,000.00 |
| GoK Contract Sum | KES 1,300,000,000.00 |
| Foreign Contract Sum | KES 0.00 |
| Cumulative Expenditure | KES 0.00 |
| Outstanding Cost | KES 0.00 |
Beneficiaries
| Target Households | 8,000 |
| Target Population | 40,000 |