Burindaya Village Borehole

Project Detail Report

Overview

StatusOngoing
TypeBorehole
AgencyTana Water Works Development Agency
ProgramCross- County Bulk Water & Sanitation Program
Progress50.00%

Location Information

CountyMeru
ConstituencyTigania West
WardKianjai
SettingRural
Coordinates,

Timeline & Impact

Start Date2022-07-11
Planned End DateN/A
Actual End DateN/A
ContractorEast Africa Aquatech Limited
ConsultantN/A
Target AreasBurindaya Village
Scope of Works Drilling, development and test pumping  Borehole drilled to 150m depth and 58m3/h yield obtained
ImpactsProvision of safe water when complete
ChallengesGOK late disbursments
RemarksDrilling complete, awaiting equipping and last mile connectivity

Project Cost

Total Contract Sum (GoK + Foreign)KES 2,086,004.80
GoK Contract SumKES 2,086,004.80
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 0.00
Outstanding CostKES 2,086,004.80

Funding Sources

SourceTypeAmount (KES)
Gok Grant 2,086,004.80

Beneficiaries

Target Households200
Target Population1,000