Overview
| Status | Ongoing |
| Type | Borehole |
| Agency | Tana Water Works Development Agency |
| Program | Universal Health Coverage Program |
| Progress | 63.00% |
Location Information
| County | Kirinyaga |
| Constituency | Mwea |
| Ward | Nyangati |
| Setting | Urban |
| Coordinates | -0.619697, 37.370919 |
Timeline & Impact
| Start Date | 2021-09-02 |
| Planned End Date | N/A |
| Actual End Date | N/A |
| Contractor | Octagon Builders & General Suppliers |
| Consultant | N/A |
| Target Areas | Kimbimbi Hospital |
| Scope of Works | Connect to Mwea Makima Water system 2.5km away;
Erection of 50m3; Pressed Steel Elevated Tank;
Improvement of rain water harvesting facilities |
| Impacts | Provision of safe water |
| Challenges | GOK late disbursments . Contractor citing financial constraints |
| Remarks | Need for Improved Coordination and Timely Funding |
Project Cost
| Total Contract Sum (GoK + Foreign) | KES 7,113,109.00 |
| GoK Contract Sum | KES 7,113,109.00 |
| Foreign Contract Sum | KES 0.00 |
| Cumulative Expenditure | KES 3,874,611.00 |
| Outstanding Cost | KES 0.00 |
Funding Sources
| Source | Type | Amount (KES) |
| Gok |
Grant |
7,113,109.00 |
Beneficiaries
| Target Households | 1 |
| Target Population | 500 |