Kiamuguongo Water Supply Project

Project Detail Report

Overview

StatusOngoing
TypeWater Supply Project
AgencyTana Water Works Development Agency
ProgramCross- County Bulk Water & Sanitation Program
Progress5.00%

Location Information

CountyKirinyaga
ConstituencyNdia
WardKiine
SettingRural
Coordinates,

Timeline & Impact

Start Date2025-02-01
Planned End Date2025-07-03
Actual End DateN/A
ContractorAbsa Chemicals Ltd
ConsultantN/A
Target AreasKiine Residents
Scope of Works Rehabilitation of the intake  Rehabilitation of the existing water supply scheme  Extension of existing pipelines
ImpactsProvision of safe water for domestic and agricultural use.
ChallengesGOK late disbursments . Contractor citing financial constraints
RemarksNeed for Improved Coordination and Timely Funding

Project Cost

Total Contract Sum (GoK + Foreign)KES 72,305,339.82
GoK Contract SumKES 72,305,339.82
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 0.00
Outstanding CostKES 0.00

Funding Sources

SourceTypeAmount (KES)
Gok Grant 72,305,339.82

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2023/24 Approved GOK 25,000,000.00

Beneficiaries

Target Households500
Target Population2,500