Kivue Village Borehole

Project Detail Report

Overview

StatusCompleted
TypeBorehole
AgencyTana Water Works Development Agency
ProgramCross- County Bulk Water & Sanitation Program
Progress100.00%

Location Information

CountyEmbu
ConstituencyMbeere North
WardMuminji
SettingRural
Coordinates,

Timeline & Impact

Start DateN/A
Planned End DateN/A
Actual End Date2021-09-02
ContractorOctagon Builders and General Supplies Central Water Company Limited
ConsultantN/A
Target AreasKivue Secondary School and Kivue village
Scope of Works Drilling, development, test pumping and equipping with solar powered pumping system
ImpactsImproves access to clean water and create employment opportunities
ChallengesLate disbursement of government funds.
RemarksNeed for Improved Coordination and Timely Funding

Project Cost

Total Contract Sum (GoK + Foreign)KES 4,835,969.00
GoK Contract SumKES 4,835,969.00
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 3,658,951.00
Outstanding CostKES 1,177,018.00

Funding Sources

SourceTypeAmount (KES)
Gok Grant 4,835,969.00

Beneficiaries

Target Households50
Target Population300