Uvarire Village Borehole

Project Detail Report

Overview

StatusCompleted
TypeBorehole
AgencyTana Water Works Development Agency
ProgramCross- County Bulk Water & Sanitation Program
Progress100.00%

Location Information

CountyEmbu
ConstituencyMbeere North
WardEvurore
SettingRural
Coordinates,

Timeline & Impact

Start DateN/A
Planned End DateN/A
Actual End DateN/A
ContractorMaji Africa Ltd
ConsultantN/A
Target AreasUvarire Primary School and Uvarire Village
Scope of Works Drilling, development, test pumping and equipping with solar powered pumping system
ImpactsImproves access to clean water and create employment opportunities
ChallengesLate disbursement of government funds.
RemarksNeed for Improved Coordination and Timely Funding

Project Cost

Total Contract Sum (GoK + Foreign)KES 7,365,145.00
GoK Contract SumKES 7,365,145.00
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 3,056,570.00
Outstanding CostKES 4,308,575.00

Funding Sources

SourceTypeAmount (KES)
Gok Grant 7,365,145.00

Beneficiaries

Target Households1
Target Population1,050