Mbeere South Water Supply Project

Project Detail Report

Overview

StatusOngoing
TypeWater Supply Project
AgencyTana Water Works Development Agency
ProgramCross- County Bulk Water & Sanitation Program
Progress20.50%

Location Information

CountyEmbu
ConstituencyMbeere South
WardKiambere
SettingRural
Coordinates,

Timeline & Impact

Start DateN/A
Planned End DateN/A
Actual End DateN/A
ContractorNanchang Municipal Engineering Development Company
ConsultantN/A
Target AreasParts of Kiritiri, Mwanyari and Lower Mbeti
Scope of WorksLot II-Kamburu Water supply system (Include water Pumping system and Laying of about 45 KM of water pipeline of varying Diameter Dn 63 – Dn 250 mm, With water treatment plant( WTP) of 10,000m3/day)
ImpactsImproves access to clean water and create employment opportunities
ChallengesLand acquization
RemarksNeed for Improved Coordination and Timely Funding

Project Cost

Total Contract Sum (GoK + Foreign)KES 789,689,755.80
GoK Contract SumKES 789,689,755.80
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 63,699,847.51
Outstanding CostKES 0.00

Funding Sources

SourceTypeAmount (KES)
Gok Grant 789,689,755.80

Beneficiaries

Target Households7,500
Target Population37,500