Project Detail Report
| Status | Proposed |
|---|---|
| Type | Augmentation Project |
| Agency | Tana Water Works Development Agency |
| Program | National Urban Water Supply and Sanitataion Program (NUWSSP) Ph II |
| Progress | 0.00% |
| County | Embu |
|---|---|
| Constituency | Mbeere North |
| Ward | Kiambere |
| Setting | Urban |
| Coordinates | , |
| Start Date | N/A |
|---|---|
| Planned End Date | N/A |
| Actual End Date | N/A |
| Contractor | N/A |
| Consultant | N/A |
| Target Areas | Ena and Ishiara |
| Scope of Works | Construction of water intake on Thuci River, Laying of 3.5km raw water main, 15,000m3/day Water treatment plant, 6km treated Water main, Water storage tank ( 2000m3) and 13.5km reticulation network •Sewer Project - Sewer treatment plant of 3,500m3/day, Laying of 15km lateral sewer lines and Laying of 5km trunk sewer line b) Ena and Environs •Water Project - Construction of water intake on Thuci River, Laying of 13km DN 600mm raw water main, 24,000m3/day Water treatment plant, 35km treated Water main, Water storage tank and 42 km reticulation network. • Sewer Project - Sewer treatment plant of 4,500m3/day , Laying of 10km lateral sewer lines and Laying of 5km of trunk sewer line |
| Impacts | Improves access to clean water and create employment opportunities |
| Challenges | Sourcing for the funds which may delay |
| Remarks | Feasibility Study done waiting for the Final Designs |
| Total Contract Sum (GoK + Foreign) | KES 1.75 |
|---|---|
| GoK Contract Sum | KES 0.00 |
| Foreign Contract Sum | KES 1.75 |
| Cumulative Expenditure | KES 0.00 |
| Outstanding Cost | KES 0.00 |
| Target Households | 20,000 |
|---|---|
| Target Population | 10,000 |