Rehabilitation of Nginda Ngandori Water Project

Project Detail Report

Overview

StatusProposed
TypeRehabilitation Project
AgencyTana Water Works Development Agency
ProgramNational Urban Water Supply and Sanitataion Program (NUWSSP) Ph II
Progress0.00%

Location Information

CountyEmbu
ConstituencyManyatta
WardMbeti North
SettingUrban
Coordinates,

Timeline & Impact

Start DateN/A
Planned End DateN/A
Actual End DateN/A
ContractorN/A
ConsultantN/A
Target AreasNginda ngandori areas and its environs
Scope of WorksRehabilitating the existing water supply infrastructure
ImpactsImproves access to clean water and create employment opportunities
ChallengesSourcing for the funds which may delay
RemarksFeasibility Study done waiting for the Final Designs

Project Cost

Total Contract Sum (GoK + Foreign)KES 140.00
GoK Contract SumKES 0.00
Foreign Contract SumKES 140.00
Cumulative ExpenditureKES 0.00
Outstanding CostKES 0.00

Beneficiaries

Target Households1,000
Target Population5,000