Overview
| Status | Proposed |
| Type | Dam |
| Agency | Tana Water Works Development Agency |
| Program | Cross- County Bulk Water & Sanitation Program |
| Progress | 0.00% |
Location Information
| County | Embu |
| Constituency | Mbeere North |
| Ward | Ruguru/ngandori |
| Setting | Rural |
| Coordinates | , |
Timeline & Impact
| Start Date | N/A |
| Planned End Date | N/A |
| Actual End Date | N/A |
| Contractor | N/A |
| Consultant | N/A |
| Target Areas | Magutu area and its envrons |
| Scope of Works | N/A |
| Impacts | Improves access to clean water and create employment opportunities |
| Challenges | Lack of GOK funds may delay commencement of the works |
| Remarks | Feasibility Study done waiting for the Final Designs |
Project Cost
| Total Contract Sum (GoK + Foreign) | KES 60.00 |
| GoK Contract Sum | KES 0.00 |
| Foreign Contract Sum | KES 60.00 |
| Cumulative Expenditure | KES 0.00 |
| Outstanding Cost | KES 0.00 |
Beneficiaries
| Target Households | 40 |
| Target Population | 200 |