Tungu Dam

Project Detail Report

Overview

StatusProposed
TypeDam
AgencyTana Water Works Development Agency
ProgramPublic Private Partnership (PPP)
Progress0.00%

Location Information

CountyTharaka Nithi
ConstituencyChuka/Igambang’ombe
WardIgambang’ombe Ward
SettingUrban
Coordinates-0.396981, 37.812526

Timeline & Impact

Start DateN/A
Planned End DateN/A
Actual End DateN/A
ContractorN/A
ConsultantN/A
Target AreasIgamba ngombe ward and its envrons
Scope of WorksConstruct dam with approximately 30million m3 capacity on Tungu River
ImpactsImproves access to clean water and create employment opportunities
ChallengesDelay may happen due to unavailability of funds
RemarksFeasibility Study Done, waiting for the Final Designs

Project Cost

Total Contract Sum (GoK + Foreign)KES 700,000,000.00
GoK Contract SumKES 0.00
Foreign Contract SumKES 700,000,000.00
Cumulative ExpenditureKES 0.00
Outstanding CostKES 0.00

Beneficiaries

Target Households600
Target Population3,000