| Start Date | N/A |
| Planned End Date | N/A |
| Actual End Date | N/A |
| Contractor | Hampton Construction Limited |
| Consultant | N/A |
| Target Areas | Cheptulel TTI
Cheptulel Boys Secondary
Kokwombeses Secondary
Cheptulel Girls Secondary
Cheptule Primary
Arpollo Primary
Sapulmoi Primary
Chemaley Primary
Kosilot Primary
Cheptulel Shoppping Centre
Administrative areas |
| Scope of Works | 1. Intake works;
2. Gravity Main Pipeline – 2.50 Km
a) 4" dia Galvanized Iron Class B Section – 1.00 Km
b) HDPE Diameter 110 mm – 1.50 Km
3. Distribution Pipelines
a) Ksaa -TTI Tank Pipeline (1 Km long 3" GI Pipe)
b) TTI line (0.8 Km long Diameter 63 mm)
c) Cheptulel Primary Line (2.2 Km long Diameter 75 mm)
4. Rehabilitation of existing 3 No. Masonry Tanks
5. Construct a 2 m3 Break Pressure Tank
6. Other Civil Works |
| Impacts | Improved security status across the two communities
Improved access to water
Cheptulel is now more habitable as evidenced by improved settlement increasing land productivity and enhanced livelihoods
Re-opening of closed schools |
| Challenges | Insecurity within the project area
Difficult terrain |
| Remarks | The project is complete and operational
Request for additional funds to implement phase II of the project |