Mtembur-Kitalakapel Water Supply Project

Project Detail Report

Overview

StatusCompleted
TypeUnknown
AgencyNorth Rift Valley Water Works Developmnet Agency
ProgramUnknown Program
Progress100.00%

Location Information

CountyWest pokot
ConstituencyKapenguria
WardMnagei and Riwo Wards
SettingN/A
Coordinates,

Timeline & Impact

Start Date2023-02-06
Planned End DateN/A
Actual End Date2024-03-06
ContractorN/A
ConsultantN/A
Target AreasN/A
Scope of Works• Completion of weir at Mtembur river • 25M3 Composite Filtration Unit CFU • 50M3 Elevated steel tank • 500M3 masonry tank • 1KM rising main • 15.7KM distribution line • Solarization
ImpactsN/A
ChallengesN/A
RemarksThis project was implemented under WSTF through Ending Drought Emergencies - Climate Proofed Infrastructure program.The project is serving population of 4,385 people as per the 2019 population census in addition to learning institutions and government offices.

Project Cost

Total Contract Sum (GoK + Foreign)KES 83.00
GoK Contract SumKES 83.00
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 0.00
Outstanding CostKES 0.00