Project Detail Report
| Status | Completed |
|---|---|
| Type | Springs: Extension of pipeline |
| Agency | North Rift Valley Water Works Developmnet Agency |
| Program | GOK Funded Projects |
| Progress | 100.00% |
| County | Turkana |
|---|---|
| Constituency | Turkana Central |
| Ward | Kangatotha/ Kalokol |
| Setting | Rural |
| Coordinates | , |
| Start Date | 2024-10-04 |
|---|---|
| Planned End Date | 2024-10-08 |
| Actual End Date | 2024-03-09 |
| Contractor | Rhumas Co. Ltd |
| Consultant | N/A |
| Target Areas | Eliye, Wadach, Lobolo, Loyolo,.. & Kalokol |
| Scope of Works | Rehabilitation of intake and laying of 10km water distribution main line |
| Impacts | Residents accessing better quality water (Non-saline) closer to settlements |
| Challenges | High demand versus low supply, vulnerable infrastructure |
| Remarks | Phase 1 of the project is complete and operational. Phase 2 undertaken by CRVWWDA for completion of pipeline to Kalokol, 80% complete |
| Total Contract Sum (GoK + Foreign) | KES 19,405,100.00 |
|---|---|
| GoK Contract Sum | KES 19,405,100.00 |
| Foreign Contract Sum | KES 0.00 |
| Cumulative Expenditure | KES 18,218,230.00 |
| Outstanding Cost | KES 0.00 |
| Source | Type | Amount (KES) |
|---|---|---|
| Gok | Grant | 20,000,000.00 |
| Fiscal Year | Stage | Funding Side | Amount (KES) |
|---|---|---|---|
| 2023/24 | Approved | GOK | 20,000,000.00 |
| Target Households | 2,000 |
|---|---|
| Target Population | 10,000 |