| Start Date | N/A |
| Planned End Date | N/A |
| Actual End Date | N/A |
| Contractor | Warmoon Construction Company |
| Consultant | N/A |
| Target Areas | Mogil and Kaptora Sub locations of Mon Location
Mogil Boarding Secondary School
Kaptora Boys Boarding School
Mogil Day Primary
Kapkein Boarding Pri School
Mogil ECDE
Kaptora ECDE
Kasar ECDE
Kantoror ECDE
Kapkein ECDE
Lower Sambirir ICT Centre |
| Scope of Works | Construction of intake
Construction of 2No. Masonry tanks at Kasar and Kantoror of capacities 50m3 and 100m3 respectively
Rehabilitation of 50m3 Korpaman Tank
Laying of 80/ 90mm gravity main in GI and HDPE 4km
Laying of distribution lines in sizes ranging OD 63mm – diameter 75mm - 6km |
| Impacts | Increased water coverage
Improved Quality of Life
Reduction in Waterborne Diseases
Better Hygiene and Sanitation
Increased Productivity
Community Cohesion
Reforestation and Soil Conservation |
| Challenges | Exisisting inter clan issues within the community which led to change of propsed intake site |
| Remarks | Interclan issues resolved andf the project is progressing well |