Overview
| Status | Ongoing |
| Type | Rehabilitation |
| Agency | North Rift Valley Water Works Developmnet Agency |
| Program | GOK Funded Projects |
| Progress | 5.00% |
Location Information
| County | N/A |
| Constituency | N/A |
| Ward | N/A |
| Setting | Urban |
| Coordinates | , |
Timeline & Impact
| Start Date | 2024-01-11 |
| Planned End Date | 2025-01-03 |
| Actual End Date | N/A |
| Contractor | Nine Eighty Eight |
| Consultant | N/A |
| Target Areas | Upper Elgon View, Sports Club |
| Scope of Works | Relocation/Upgrade of 1km diameter 315 distribution Main |
| Impacts | Reduction in non-revenue water
Improved water supply to the target areas |
| Challenges | Delays in mobilization to site |
| Remarks | Work behind schedule due to delays by the contractor |
Project Cost
| Total Contract Sum (GoK + Foreign) | KES 12,660,900.00 |
| GoK Contract Sum | KES 12,660,900.00 |
| Foreign Contract Sum | KES 0.00 |
| Cumulative Expenditure | KES 0.00 |
| Outstanding Cost | KES 0.00 |
Funding Sources
| Source | Type | Amount (KES) |
| Gok |
Grant |
15,000,000.00 |
Beneficiaries
| Target Households | 300 |
| Target Population | 1,200 |