Kapsowar Town Sewerage System

Project Detail Report

Overview

StatusProposed
TypeUnknown
AgencyNorth Rift Valley Water Works Developmnet Agency
ProgramUnknown Program
Progress0.00%

Location Information

CountyN/A
ConstituencyN/A
WardN/A
SettingN/A
Coordinates,

Timeline & Impact

Start DateN/A
Planned End DateN/A
Actual End DateN/A
ContractorN/A
ConsultantN/A
Target AreasKapsowar Town
Scope of WorksConstruction of a new sewerage system for Kapsowar Town
ImpactsN/A
ChallengesN/A
RemarksFunds for Design & Implementation being sought through the Ministry

Project Cost

Total Contract Sum (GoK + Foreign)KES 600.00
GoK Contract SumKES 600.00
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 0.00
Outstanding CostKES 0.00

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2023/24 Approved GOK 50,000,000.00

Beneficiaries

Target Households12,000
Target Population0