Drilling and Equiping of Mata Arba Borehole

Project Detail Report

Overview

StatusOngoing
TypeWater Pan
AgencyNorthern Water Works Development Agency
ProgramGOK Funded Projects
Progress10.00%

Location Information

CountyMarsabit
ConstituencySaku
WardMarsabit Central
SettingN/A
Coordinates,

Timeline & Impact

Start Date2024-10-01
Planned End Date2025-06-01
Actual End Date2026-01-06
ContractorOSB Africa Limited
ConsultantN/A
Target AreasN/A
Scope of WorksDrilling, development and test pumping
ImpactsTo Increase water storage to be used in dry periods to reduce the cost of living and inclusive growth
ChallengesInsufficient budgetary allocations
RemarksN/A

Project Cost

Total Contract Sum (GoK + Foreign)KES 10.20
GoK Contract SumKES 10.20
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 0.00
Outstanding CostKES 0.00

Beneficiaries

Target Households200
Target Population1,200