Wardeglow dam

Project Detail Report

Overview

StatusOngoing
TypeWater Pan
AgencyNorthern Water Works Development Agency
ProgramGOK Funded Projects
Progress1.00%

Location Information

CountyGarissa
ConstituencyDadaab
WardKulan
SettingN/A
Coordinates,

Timeline & Impact

Start DateN/A
Planned End DateN/A
Actual End DateN/A
ContractorMac Sisters Limited
ConsultantN/A
Target AreasN/A
Scope of WorksConstruction of 1 no. water pan, Construction of spillway, Auxiliary works
ImpactsTo Increase water storage to be used in dry periods to reduce the cost of living and inclusive growth
ChallengesInsufficient budgetary allocations
RemarksN/A

Project Cost

Total Contract Sum (GoK + Foreign)KES 20.00
GoK Contract SumKES 20.00
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 0.00
Outstanding CostKES 0.00

Beneficiaries

Target Households300