Construction works for Gatundu water supply and sewerage project

Project Detail Report

Overview

StatusOngoing
TypeWater supply,sewer lines and reticulations
AgencyAthi Water Works Development Agency
ProgramKenya Towns Sustainable Water Supply and Sanitation Program (KTSWSSP)
Progress77.50%

Location Information

CountyKiambu
ConstituencyGatundu South
WardKiamwangi, Kiganjo, Ndarugo, Ngenda
SettingRural
Coordinates-1.030187, 36.911202

Timeline & Impact

Start Date2019-02-08
Planned End Date2020-08-08
Actual End DateN/A
ContractorZhongding International Engineering Company Ltd & Jianxi Transporttation Engineering Group Corporation Kenya Ltd Jv
ConsultantRunji Consulting Group
Target AreasKiamwangi, Kiganjo, Ndarugo, Ng’enda
Scope of WorksConstruction of 3 No. New Intakes and Water Treatment Plants in Handege, Ruabora, and Ng'enda whose capacity is 9,667m3/day, 4,280m3/day, and 4,280m3/day respectively. Laying 43 Km water transmission and distribution pipeline for Gatundu, Ng'enda, Mutomo, and Kenyatta Road Areas. 58 km of Trunk and laterals Sewers to serve Gatundu town and drain to Juja Sewerage Treatment Plant. Construction of the Gatundu Water and Sewerage Company Office Building. 2,000 Last Mile Sewerage Household Connections.
ImpactsAgumenting the water supply and improving wastewater disposal.
ChallengesPemding Payments for sewerlines. delayed compensation of treated water lines.
RemarksThere should be regular inspection along the pipelines to identify leakages at early stages. Also there should be increased support to area WSP to be able to address the issue on vandalism.

Project Cost

Total Contract Sum (GoK + Foreign)KES 1,750,800,775.00
GoK Contract SumKES 0.00
Foreign Contract SumKES 1,750,800,775.00
Cumulative ExpenditureKES 1,448,309,350.00
Outstanding CostKES 302,491,425.70

Funding Sources

SourceTypeAmount (KES)
Adb Loan 1,750,800,775.00

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2021/22 Approved FOREIGN 247,383,931.60
2022/23 Approved FOREIGN 369,785,316.70
2023/24 Approved FOREIGN 258,116,128.50
2024/25 Allocated FOREIGN 210,568,420.60

Beneficiaries

Target Households35,609
Target Population122,103