Construction works for Makutano water supply and sewerage projectt

Project Detail Report

Overview

StatusOngoing
TypeSewer, Water lines and reticulations
AgencyAthi Water Works Development Agency
ProgramKenya Towns Sustainable Water Supply and Sanitation Program (KTSWSSP)
Progress95.52%

Location Information

CountyMurang'a
ConstituencyMaragua
WardIchagaki, Kambiti, Wempa, Makuyu, Maragua
SettingRural
Coordinates-0.792407, 37.130656

Timeline & Impact

Start Date2020-10-09
Planned End Date2022-04-08
Actual End DateN/A
ContractorChina Civil Engineering Construction Corporstion Kenya Ltd
ConsultantLosai Management Limited
Target AreasKenol, KInyona, Kangari, Mareira , wangu
Scope of Works48.2 km, OD 200/160 mm transmission main in MUSWASCO area, 123 Km, OD 200-50 mm Last Mile Connectivity pipelines in MWESCO area, 24.3 Km, OD 90 mm Last Mile Connectivity pipelines in GATAWASCO area, 2 No. 250 m3 masonry tanks, INo. Ablution Block at Sabasaba market, 17km of 600/450/300mm dia. DWC trunk sewer pipelines, 15.1km of 250mm dia. DWC pipes of reticulation sewers, Sewage Treatment Plant of capacity 3,000m³/d,1,000 household connections;
ImpactsAccess to water supply and improved sanitation services
ChallengesPending payments for sewerlines, deelayed compensation for land at the intake, wayleave
RemarksThere should be regular inspection along the pipelines to identify leakages at early stages. Also there should be increased support to area WSP to be able to address the issue on vandalism.

Project Cost

Total Contract Sum (GoK + Foreign)KES 924,258,513.30
GoK Contract SumKES 0.00
Foreign Contract SumKES 924,258,513.30
Cumulative ExpenditureKES 880,968,884.10
Outstanding CostKES 43,289,629.16

Funding Sources

SourceTypeAmount (KES)
Adb Loan 924,258,513.30

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2021/22 Approved FOREIGN 130,595,501.20
2022/23 Approved FOREIGN 195,211,946.40
2023/24 Approved FOREIGN 136,261,094.10
2024/25 Allocated FOREIGN 111,160,366.20

Beneficiaries

Target Households17,668
Target Population57,252