Project Detail Report
| Status | Ongoing |
|---|---|
| Type | Water Pan |
| Agency | Central Rift Valley Water Works Development Agency |
| Program | Equalization Fund Project Phase ll |
| Progress | 100.00% |
| County | Mombasa |
|---|---|
| Constituency | Mvita |
| Ward | Ganjoni/Shimanzi |
| Setting | Rural |
| Coordinates | 4.465463, 34.615016 |
| Start Date | 2024-07-03 |
|---|---|
| Planned End Date | 2024-07-30 |
| Scope of Works | Construction of Water Pan |
| Impacts | Improve access to water |
| Challenges | No challenges |