Project Detail Report
| Status | Completed |
|---|---|
| Type | Borehole |
| Agency | Lake Victoria North Water Works Development Agency |
| Program | Universal Health Coverage Program |
| Progress | 100.00% |
| County | Vihiga |
|---|---|
| Constituency | Vihiga |
| Ward | Lugaga-Wamuluma |
| Setting | Urban |
| Coordinates | 0.079829, 34.721079 |
| Start Date | N/A |
|---|---|
| Planned End Date | N/A |
| Actual End Date | N/A |
| Contractor | Gari Hills Enterprises |
| Consultant | N/A |
| Target Areas | Mukuli |
| Scope of Works | Construction of 30m3 Elevated steel tank Distribution pipeline 500m |
| Impacts | Reduction in waterborne diseases due to access to clean water and improved sanitation, leading to better overall health and reduced healthcare costs. Increased school attendance especially for girls as they spend less time collecting water and managing sanitation needs. Access to clean water and sanitation will increase productivity in the workforce, leading to improved livelihoods and economic growth, women and girls often bear the burden of collecting water, so improved water access will empower them and provide more time for other activities |
| Challenges | Insufficient budget allocation which led to delays and limitations in scope. Late disbursement of project funds |
| Remarks | It is complete and operationa;l |
| Total Contract Sum (GoK + Foreign) | KES 8,500,540.00 |
|---|---|
| GoK Contract Sum | KES 8,500,540.00 |
| Foreign Contract Sum | KES 0.00 |
| Cumulative Expenditure | KES 8,500,540.00 |
| Outstanding Cost | KES 0.00 |
| Source | Type | Amount (KES) |
|---|---|---|
| Gok | Grant | 8,500,540.00 |
| Fiscal Year | Stage | Funding Side | Amount (KES) |
|---|---|---|---|
| 2022/23 | Approved | GOK | 8,500,540.00 |
| Target Households | 250 |
|---|---|
| Target Population | 1,000 |