Project Detail Report
| Status | Completed |
|---|---|
| Type | Borehole |
| Agency | Lake Victoria North Water Works Development Agency |
| Program | Government of Kenya Development programme |
| Progress | 100.00% |
| County | Bungoma |
|---|---|
| Constituency | Kanduyi |
| Ward | Marakaru/tuuti |
| Setting | Rural |
| Coordinates | , |
| Start Date | 2024-01-03 |
|---|---|
| Planned End Date | 2024-06-03 |
| Actual End Date | 2024-01-09 |
| Contractor | Maimen |
| Consultant | N/A |
| Target Areas | Tuuti |
| Scope of Works | Drilling of the borehole, 30m3 plastic tank, on a 10m elevated tank, installation of solar pumping system distribution and reticulation pipeline |
| Impacts | Reduced waterborne diseases, Improved social economic livelihood, Reduced distances covered to access water Improved education standards |
| Challenges | Inadequate budget allocation, late disbursement of funds |
| Remarks | The project is complete and operational |
| Total Contract Sum (GoK + Foreign) | KES 9,171,257.00 |
|---|---|
| GoK Contract Sum | KES 9,171,257.00 |
| Foreign Contract Sum | KES 0.00 |
| Cumulative Expenditure | KES 0.00 |
| Outstanding Cost | KES 0.00 |
| Source | Type | Amount (KES) |
|---|---|---|
| Gok | Grant | 10,000,000.00 |
| Fiscal Year | Stage | Funding Side | Amount (KES) |
|---|---|---|---|
| 2022/23 | Approved | GOK | 10,000,000.00 |
| Target Households | 125 |
|---|---|
| Target Population | 500 |