| Start Date | N/A |
| Planned End Date | N/A |
| Actual End Date | N/A |
| Contractor | Dicom Engineering |
| Consultant | Batch Associate Limited |
| Target Areas | Lungusi,malavatown, Kakoi, Tolilet, Malichi,Musungu, malanga,Shivikwa, Tumbeni, Nguvuli, Mukhoje, Munguliro,Shitiriri,Matiori, |
| Scope of Works | Construction of intake works
construction of treatment works of capacity 2760m3/day with associated works
construction of distribution and transmission line 45km Long
construction of 3No storage tanks of combined capacity of 1850m3
Construction of 40No water kiosk
Construction of 5No Ablution blocks |
| Impacts | Reduction in waterborne diseases due to access to clean water and improved sanitation, leading to better overall health and reduced healthcare costs. Increased school attendance especially for girls as they spend less time collecting water and managing sanitation needs. Access to clean water and sanitation will increase productivity in the workforce, leading to improved livelihoods and economic growth, women and girls often bear the burden of collecting water, so improved water access will empower them and provide more time for other activities |
| Challenges | Inadequate budget allocation, late disbursement of funds |
| Remarks | Main storage tank at Malava forest completed, construction of treatment works at 10% , construction of Tolilet upstream community at 90% ,
construction of break presurre tank and RE office at 95%
The project is likely to be extended beyold the Planned completion date of 22rd March 2025.
Contractor IPC have been partially paid due to late disburcement of funds |