Kamonjil Primary School Water Project

Project Detail Report

Overview

StatusOngoing
TypeBorehole
AgencyLake Victoria North Water Works Development Agency
ProgramWater Harvesting Program
Progress90.00%

Location Information

CountyNandi
ConstituencyChesumei
WardKosirai
SettingRural
Coordinates,

Timeline & Impact

Start DateN/A
Planned End DateN/A
Actual End DateN/A
ContractorUpwork Enterprises Limited
ConsultantN/A
Target AreasKamonjil
Scope of Works1.Preliminaries and General Items. 2.Installation of solar power hybrid system and submersible pump. 3.Rising main from the borehole to elevated tank (130m length) 40mm dia. 4.Distribution line from the tank chamber (270m long) 40mm dia. 5.Construction of 4nr communal water points.
ImpactsIncreased school attendance especially for students as they spend less time collecting water. Access to clean water and has increased their productivity and provided more time for other educational activities. There has been reduction in waterborne diseases due to access to clean water and improved sanitation, leading to better overall health and reduced healthcare costs.
ChallengesInsufficient budget allocation which led to delays and limitations in scope and late disbursement of funds
RemarksThe project is complete and operational

Project Cost

Total Contract Sum (GoK + Foreign)KES 8,896,287.75
GoK Contract SumKES 8,896,287.75
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 6,527,981.00
Outstanding CostKES 1,345,090.50

Funding Sources

SourceTypeAmount (KES)
Gok Grant 10,000,000.00

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2023/24 Approved GOK 10,000,000.00

Beneficiaries

Target Households200
Target Population800