Mbakalo Water Project

Project Detail Report

Overview

StatusProposed
TypeBorehole
AgencyLake Victoria North Water Works Development Agency
ProgramGOK Funded Projects
Progress0.00%

Location Information

CountyBungoma
ConstituencyTongaren
WardMbakalo
SettingRural
Coordinates0.721056, 35.004509

Timeline & Impact

Start DateN/A
Planned End DateN/A
Actual End DateN/A
ContractorN/A
ConsultantN/A
Target AreasMbakalo B
Scope of WorksRehabilitation of the spring Construction of 5om3 Masonly sump Rehabilitation and augmentation of solar and electromechanical works Construction of 100m3 Elevated pressed steel tank Laying of rising main and distribution pipelines approximately 2Km long construction of 2No Water Kiosk construction of 4No.Communal water point
ImpactsThere will be reduction in waterborne diseases due to access to clean water leading to better overall health and reduced healthcare costs. There will be increased school attendance especially for girls as they spend less time collecting water. Access to clean water will increase productivity in the workforce, leading to improved livelihoods and economic growth, women and girls often bear the burden of collecting water, so improved water access will empower them and provide more time for other activities
ChallengesThe allocated amount(KES 5,000,000) is not enough to Complete the project
RemarksThe project requires an additional amount of 25,000,000 (Twenty-five Million Kenya shillings) for it to complete operational and serve the required target area

Project Cost

Total Contract Sum (GoK + Foreign)KES 0.00
GoK Contract SumKES 0.00
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 0.00
Outstanding CostKES 0.00

Funding Sources

SourceTypeAmount (KES)
Gok Grant 5,000,000.00

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2024/25 Allocated GOK 5,000,000.00

Beneficiaries

Target Households750
Target Population3,000