Matunda sub county Hospital

Project Detail Report

Overview

StatusProposed
TypeBorehole
AgencyLake Victoria North Water Works Development Agency
ProgramUniversal Health Coverage Program
Progress0.00%

Location Information

CountyKakamega
ConstituencyLikuyani
WardNzoia
SettingUrban
Coordinates0.825649, 35.115860

Timeline & Impact

Start DateN/A
Planned End DateN/A
Actual End DateN/A
ContractorN/A
ConsultantN/A
Target AreasNabiswa
Scope of WorksBorehole Drilling and casing Electromechanical and civil works Pipeline laying of approximately 1.5Km Long Construction of 5No Communal water point Construction of communal water point Construction of 50m3 Elevated pressed steel tank
ImpactsReduction in waterborne diseases due to access to clean water and improved sanitation, leading to better overall health and reduced healthcare costs. Increased school attendance especially for girls as they spend less time collecting water and managing sanitation needs. Access to clean water and sanitation will increase productivity in the workforce, leading to improved livelihoods and economic growth, women and girls often bear the burden of collecting water, so improved water access will empower them and provide more time for other activities
ChallengesThe allocated money has never been disbursed
RemarksWe need Kshs. 10,000,000 to complete the project fully. The borehole yield will be determined after drilling

Project Cost

Total Contract Sum (GoK + Foreign)KES 0.00
GoK Contract SumKES 0.00
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 0.00
Outstanding CostKES 0.00

Funding Sources

SourceTypeAmount (KES)
Gok Grant 7,500,000.00

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2022/23 Approved GOK 7,500,000.00

Beneficiaries

Target Households750
Target Population3,000