| Start Date | N/A |
| Planned End Date | N/A |
| Actual End Date | N/A |
| Contractor | N/A |
| Consultant | Cas Consultant LTD |
| Target Areas | Kapsabet town |
| Scope of Works | Construction of approximately 65Km sewer lines, Construction of 4,378 m3/d and 7,389 m3/d waste water treatment plants at North and South sites respectively, Construction of on-site sanitation facilities (ablution blocks), Provision of exhauster truck and flushing units |
| Impacts | Reduction in waterborne diseases due to access to clean water and improved sanitation, leading to better overall health and reduced healthcare costs. Increased school attendance especially for girls as they spend less time collecting water and managing sanitation needs. Access to clean water and sanitation will increase productivity in the workforce, leading to improved livelihoods and economic growth, women and girls often bear the burden of collecting water, so improved water access will empower them and provide more time for other activities |
| Challenges | The project is yet to start |
| Remarks | Awaiting allocated funds |