| Start Date | N/A |
| Planned End Date | N/A |
| Actual End Date | N/A |
| Contractor | Q-plus Contractors Limited |
| Consultant | l |
| Target Areas | Chepkowo, Tirorok, Kipteka |
| Scope of Works | Rehabilitation works for existing gravity main, Rehabilitation of Existing Intake on River Chepkowo,Rehabilitation of Existing Intake on River Tirorok, Extension to Kiptega primary school, Construction water kiosks. |
| Impacts | Reduction in waterborne diseases due to access to clean water and improved sanitation, leading to better overall health and reduced healthcare costs. Increased school attendance especially for girls as they spend less time collecting water and managing sanitation needs. Access to clean water and sanitation will increase productivity in the workforce, leading to improved livelihoods and economic growth, women and girls often bear the burden of collecting water, so improved water access will empower them and provide more time for other activities |
| Challenges | Project stalled at 90% completion. Pending works include: Rehabilitation of damaged/Vandalized pipelines and Last Mile Connectivity |
| Remarks | Required works packaged and request for financining was made to the Ministry in the 1st Quarter of FY2024/2025 |