Short Term Action Plan

Project Detail Report

Overview

StatusOngoing
TypeWater Supply,
AgencyLake Victoria South Water Works Development Agency
ProgramKisumu Water & Sanitation Program
Progress1.00%

Location Information

CountyKisumu
ConstituencyKisumu Central
WardNyalenda B, Market Milimani
SettingUrban
Coordinates-0.125822, 34.741486

Timeline & Impact

Start Date2006-01-04
Planned End Date2007-01-07
Actual End Date2007-01-11
ContractorKundan Singh
ConsultantOtieno Odongo
Target AreasDunga Intake, CBD
Scope of WorksNew intake structure and suction pipes in Lake Victoria at Dunga 3 new pumps and associated electrical items at Dunga treatment works DN400 transmission pipeline from Dunga treatment works to Kibuye and Watson reservoirs
ImpactsIncreased water production Increased access to water supply
ChallengesWayleave acquisition Slow GoK disbursement
RemarksCompleted and handed over to KIWASCO

Project Cost

Total Contract Sum (GoK + Foreign)KES 473,000.00
GoK Contract SumKES 43,000.00
Foreign Contract SumKES 430,000.00
Cumulative ExpenditureKES 473,000.00
Outstanding CostKES 0.00

Funding Sources

SourceTypeAmount (KES)
Gok Grant 43,000.00
Afd Loan 430,000.00

Beneficiaries

Target Households11,000
Target Population100,000