LTAP Works Package 3

Project Detail Report

Overview

StatusOngoing
TypeSanitation
AgencyLake Victoria South Water Works Development Agency
ProgramKisumu Water & Sanitation Program
Progress1.00%

Location Information

CountyKisumu
ConstituencyKisumu East
WardNyalenda A,Manyatta B
SettingUrban
Coordinates-0.119272, 34.775875

Timeline & Impact

Start DateN/A
Planned End DateN/A
Actual End DateN/A
ContractorVictory Const. Co/Zhonghao
ConsultantSeureca East Africa Ltd. in JV with SEURECA Consulting Engineers
Target AreasNyalenda
Scope of WorksRehabilitation (Excavation and disludging) of Nyalenda ponds to achieve 11,000m3/day waste treatment capacity Laying of 20Km sewer pipeline Rehabilitation and upgrading of 3 No pump stations. Construction of 2 No sewerage pump stations
ImpactsIncreased sewer connection Improve quality of effluent
ChallengesWayleave acquisition Slow GoK disbursement
RemarksCompleted and handed over to KIWASCO

Project Cost

Total Contract Sum (GoK + Foreign)KES 812,371,408.64
GoK Contract SumKES 73,851,946.24
Foreign Contract SumKES 738,519,462.40
Cumulative ExpenditureKES 812,371,408.64
Outstanding CostKES 0.00

Funding Sources

SourceTypeAmount (KES)
Gok Grant 73,851,946.24
Afd Loan 738,519,462.40

Beneficiaries

Target Households25,000
Target Population125,000